A generous bequest was left to the Pequannock Township Public Library by the late Virginia Forde. The bequest was designated to cover the cost of an expansion to the Children’s Department, on the Newark Pompton Turnpike side of the building that will mirror the existing children’s wing.

The project is moving forward and any updates to the project will be noted on this page.

Grand opening celebration, 5/21/18:

[metaslider id=1846]

Update 11/29/17:

Brick work has begun.

Update 11/7/17:

The bricks are here and electrical work is being done.

Update 10/20/17:

10-20-17_1

Roof work has begun!

Update 10/10/17:

Framing is almost complete!

Update: 9/25/17:

9-25-17_1A

Framing has begun!

Update: 9/21/17:

9-21-17_cropped

The foundation has been poured.

Update 9/15/17:

9-15-17

Construction is under way!  is getting ready to pour the cement for the foundation. You can see a larger version of the image above by clicking on it.

Update 8/9/2017: The construction fence is in place at the front of the Library. Reliable NYC reports that the building permits are under review at the Township.

Update 7/20/2017: Reliable NYC, LLC of Randolph NJ was awarded the contract for the project.  More details to come in early August.

In the News:
“Construction of Pequannock Library Addition Set to Begin Soon” February 3, 2016:http://www.northjersey.com/story/news/morris/butler/2016/02/03/construction-of-pequannock-library-addition-set-to-begin-soon/94461306/

“Pequannock Library Looks to Expand” Monday, April 4, 2016:http://www.northjersey.com/story/news/morris/butler/2016/04/03/pequannock-library-looks-to-expand/94593948/